Data and Facts
Lakeside Park

 

Total area                                 
of it Natura 2000
of it landscape protection area      

Capacity utilization
Companies
Employees
 
24,6ha
7,2ha
7,9ha

99% (update 01|2021)
70 (update 01|2021)
ca 1,400 (update 01|2021)

 
 
Lakeside B01-B10

 

Start of construction                         
Completion
Construction stages
Number of buildings
Gross loor area
Useful area
Total investment
2003
2010
3
10
ca 30,100 m²
ca 24,400 m²
€ 54 Mio.

Lakeside B11-B12

 

Start of construction                         
Completion
Construction stages
Number of buildings
Gross floor area
Useful area
Total investment
2014
2015
1
2
ca 8,400 m²
ca 6,500 m²
€21,5 Mio.

Lakeside B13

 

Start of construction               
Completion
Gross floor area
Useful area
Total investment
Used by AAU|JR
Useful area excl. AAU|JR
 
2018
2020
ca 5,200 m²
ca 3,900 m²
€ 13 Mio.
ca 1,800 m²
ca 2,500 m²
 
 
Lakeside B15 (under construction)

 

Start of construction    
Completion                          
Gross floor area
Total investment
Parking garage
Box storage
2020
2021
ca 4,000 m²
€ 17 Mio.
545 parkings
56